Projects

Bagworth Road Point of Connection (PoC) – Detailed Design

Bagworth, Leicestershire, UK
27 Aug 2025

Groundline Engineering’s detailed design for NGED’s Bagworth Road PoC enabled a 49.9MW solar farm connection by replacing and repositioning a tower, resolving clearance challenges, and delivering a robust, standards-compliant construction package.

Product(s): 
Design Engineering
Service(s): 
No items found.

Client: National Grid Electricity Distribution (NGED)
Project: UK0360 – Bagworth Road PoC
Location: Bagworth, Leicestershire, UK
Delivery Partner: Groundline Engineering

The Client

National Grid Electricity Distribution (NGED) is a leading electricity distribution network operator in the UK, responsible for delivering power to millions of homes and businesses across the Midlands, South West, and Wales.

The Need

To enable the connection of a new 49.9MW Stones Hollow PV Solar Farm to the existing 132kV overhead line, NGED required a detailed design for a new point of connection (PoC). The preferred solution involved replacing an existing tower with a new terminal tower and integrating downleads to gantries.

What We Did

Groundline Engineering was brought on board to handle the detailed design for the best solution. Here’s what we did:

  • Replacing an existing tower with a new tower, rotated and repositioned to facilitate a loop-in loop-out configuration.
  • Conducting a full topographical survey and PLS CADD modelling of the relevant towers.
  • Performing structural analysis and foundation load comparisons for the relevant towers.
  • Designing new uplift/compression pad and column foundations for the new tower.
  • Ensuring compliance with ENATS 43-125 and BS EN 50341 standards for electrical and structural reliability.
  • Delivering a comprehensive suite of construction documents, including wire clearance diagrams, erection stringing charts, and foundation drawings.

Challenges & Solutions

Key challenges included managing clearance infringements and ensuring structural integrity under extreme weather conditions. Groundline addressed these by:

  • Installing suspended tension sets to resolve ground clearance issues.
  • Accepting minor over-utilization of the existing OPGW under a 1-in-500-year ice event, justified by probabilistic design analysis.
  • Recommending further wire clearance checks around gantry structures to ensure safe dropper arrangements.

Results

The final design confirmed that all towers met or exceeded required reliability levels. Existing foundations were deemed sufficient, avoiding costly upgrades. The project delivered a robust, standards-compliant design ready for construction, enabling NGED to move forward with the solar farm connection confidently.

Related Projects

No items found.
View all Projects